What Is a WIP Report? A Contractor's Guide

The WIP report tells you which jobs are making money, which are fading, and how much of your cash is really yours. Here's how to read one and build it every month.

BF
BuildFlash Finance Team · 9 min read

A work-in-progress (WIP) report is a job-by-job schedule that compares what you've billed on each open contract with what you've actually earned. It's the report your surety asks for, the one your banker reads first, and the one that tells you whether this month's profit is real.

What is a WIP report?

A WIP report lists every open job alongside its contract value, costs to date, estimated cost to complete, percent complete, earned revenue, and billings. The difference between earned revenue and billings shows whether each job is overbilled or underbilled.

Because construction revenue is recognized over time with the percentage-of-completion method, the WIP is what turns a stack of invoices and cost reports into an honest income statement.

The columns that matter

ColumnWhat it tells you
Contract valueOriginal contract plus approved change orders
Total estimated costCosts to date plus the PM's cost to complete
Percent completeCosts to date ÷ total estimated cost
Earned revenuePercent complete × contract value
Billings to dateEverything invoiced on the job so far
Over / (under) billingBillings minus earned revenue
Projected gross profitContract value minus total estimated cost

How to build one every month

  1. 1Close AP and payroll so job costs are complete through month end.
  2. 2Have each PM update cost to complete from the field, not from the budget.
  3. 3Update contract values for approved change orders; track pending ones separately.
  4. 4Pull billings to date from your pay applications.
  5. 5Calculate percent complete, earned revenue, and over/under billing.
  6. 6Book the over/under billing adjustment to the general ledger.
  7. 7Review fade job by job with the PMs before you close the month.

Warning signs to look for

  • A job that stays underbilled for two or more months in a row
  • Projected margin dropping from month to month (gross profit fade)
  • Large overbillings with little work left to do
  • Percent complete jumping without a matching jump in field progress

Where BuildFlash fits

BuildFlash builds your WIP every month as part of close, reviews fade with your PMs, and delivers a surety-ready package. You get the report without hiring a controller to build it.

Terms in this guide

Frequently asked questions

Keep reading

All guides

Done-for-you construction finance

Get your WIP, job costing, and close done every month.

BuildFlash runs your monthly finance on top of the software you already use, with a fractional CFO reviewing the numbers with you.

Book Intro Call