What is underbilling?

Definition

Costs and estimated earnings in excess of billings: you've earned more than you've invoiced on a job. It's recorded as an asset on the balance sheet.

What it means

Underbilling means you've done work you haven't billed for. Sometimes that's timing: a pay app is about to go out. Often it's a signal of unapproved change orders, missed billings, or costs running over estimate.

Underbilling

Underbilling = Earned revenue − Billings to date (when positive)

Why sureties look closely

Sureties and lenders often discount underbillings because they can hide cost overruns. A job that stays underbilled month after month deserves a closer look at its cost to complete.

Billings in excess of costs and estimated earnings: you've invoiced more than you've earned on a job. It's recorded as a liability on the balance sheet.

A written amendment to a construction contract that changes its scope, price, or schedule after the contract is signed.

The maximum size of a single job and the total backlog a surety will bond for a contractor, based largely on working capital, equity, and track record.

Guides that cover this

Reporting & WIP

What Is a WIP Report? A Contractor's Guide

The WIP report tells you which jobs are making money, which are fading, and how much of your cash is really yours. Here's how to read one and build it every month.