How to Build a 13-Week Cash Flow Forecast for Construction

Profitable contractors still run out of cash. A week-by-week forecast built from pay apps, retainage, and payroll shows the crunch before it hits.

BF
BuildFlash Finance Team · 7 min read

Construction cash moves in lumps: payroll every week, pay apps once a month, retainage at the end. A 13-week forecast maps those lumps so you know when you'll be tight and how much room you have to take on new work.

Why 13 weeks

Thirteen weeks is one quarter, long enough to see past the next pay cycle and short enough to forecast with real numbers rather than guesses.

Forecast cash in

  • Approved pay applications and their expected payment dates
  • Upcoming billings from the schedule of values
  • Retainage releases tied to substantial completion
  • Change orders only once they're approved

Forecast cash out

  • Weekly payroll and burden
  • Subcontractor and supplier payments, net of retainage payable
  • Equipment, loan, and lease payments
  • Insurance, taxes, and overhead

Terms in this guide

Frequently asked questions

Keep reading

All guides

Reporting & WIP

What Is a WIP Report? A Contractor's Guide

The WIP report tells you which jobs are making money, which are fading, and how much of your cash is really yours. Here's how to read one and build it every month.

Done-for-you construction finance

Get your WIP, job costing, and close done every month.

BuildFlash runs your monthly finance on top of the software you already use, with a fractional CFO reviewing the numbers with you.

Book Intro Call